An efficient method for the construction of bridge piers

ENGINEERING STRUCTURES
  • S Nasir
  • ,
  • S Gupta
  • ,
  • H Umehara
  • ,
  • Hirasawa, I

23
9
開始ページ
1142
終了ページ
1151
記述言語
英語
掲載種別
DOI
10.1016/S0141-0296(01)00003-7
出版者・発行元
ELSEVIER SCI LTD

In this paper, a new method for the construction of bridge piers using precast prestressed concrete (PPC) panels as formwork is proposed in order to increase the efficiency of construction. Scaled down experiments were performed to check the feasibility of the proposed method. Experiments were carried out on six different reinforced concrete column specimens. These experiments were performed to check whether the PPC panels acted as an integral part of the structure due to good bonding between panels and core concrete. Load-displacement behavior, crack pattern and other experimental data were analyzed and the experimental results compared with numerical simulations to check the effectiveness of the construction method. It was interesting to observe that the use of panels did not create any weakness in the structural behavior of the specimen and can be used effectively for the construction of bridge piers. (C) 2001 Elsevier Science Ltd. All rights reserved.

リンク情報
DOI
https://doi.org/10.1016/S0141-0296(01)00003-7
CiNii Articles
http://ci.nii.ac.jp/naid/80012472851
Web of Science
https://gateway.webofknowledge.com/gateway/Gateway.cgi?GWVersion=2&SrcAuth=JSTA_CEL&SrcApp=J_Gate_JST&DestLinkType=FullRecord&KeyUT=WOS:000169968000011&DestApp=WOS_CPL
ID情報
  • DOI : 10.1016/S0141-0296(01)00003-7
  • ISSN : 0141-0296
  • CiNii Articles ID : 80012472851
  • Web of Science ID : WOS:000169968000011

エクスポート
BibTeX RIS